
সূচিপত্র
In early 2026, the construction of a new facility for a metal processing enterprise in Kazakhstan reached the equipment installation phase. Each of the four main workshops required a 10-ton premium overhead crane. Featuring a span of 18.92 meters and a lifting height of 7.68 meters, to handle daily steel lifting and the loading and unloading of finished products. The order was urgent, and the delivery deadline coincided with the Chinese New Year holiday. We faced a triple challenge: tight schedules, component shortages, and a lack of available electrical parts. Nevertheless, we maintained production throughout the holiday, delivering all four cranes to the client’s workshops on schedule and ensuring not a single day of delay in the installation timeline.
For the new factory of this metal processing enterprise in Kazakhstan, a simultaneous construction plan involving four workshops was adopted, with completion deadlines for key project milestones clearly locked into the contract. Premium overhead cranes play a pivotal role in the critical path of such factory construction projects. Once the crane rails are laid and calibrated, the premium overhead cranes must be hoisted into position immediately. This is because the subsequent delivery and installation of all heavy production line equipment, ranging from machinery units and molds to modular sections of automated production lines. Relies entirely on these workshop premium overhead cranes for lifting. Without the cranes in place, heavy equipment cannot be unloaded or vertically hoisted to installation sites, causing the entire workshop’s equipment installation process to grind to a halt.
The timing presented an even greater challenge. When the client officially placed the order in January 2026, the Chinese New Year holiday was fast approaching. During the period spanning roughly two weeks before and two weeks after the holiday, upstream suppliers shut down, long-distance domestic transport capacity contracted sharply, and factories halted operations. The entire supply chain effectively entered a state of total or partial standstill.
Yet, the client chose to award us the order on the eve of the holiday for one key reason: we do not stop production during the Chinese New Year. DAFANGCRANE’s production base is running critical processes around the holidays, with core teams on duty and production lines running. The client understood this well. Only a supplier that can maintain production capacity during the Chinese New Year could have secured this order.
Once the order was confirmed, three overlapping practical challenges arose simultaneously.
Take the hoisting motor—the “heart” of the premium overhead crane, as an example. During the Spring Festival holiday, upstream manufacturers of metallurgical crane motors suspended production as is customary, and the supply of matching gearboxes, brakes, and electrical control components also dried up.
However, DAFANGCRANE had already stockpiled key materials in anticipation of urgent orders. The hoisting motors, hardened-gear reducers, and electromagnetic brakes for the 4 premium overhead cranes. Along with electrical components such as PLCs, variable frequency drives (VFDs), contactors, and relays, all had been secured and separately inventoried in advance. Consequently, production lines continued to run throughout the holiday without any interruption in material supply.

The client’s factory construction schedule was strictly governed by contractual terms, leaving no room for flexible adjustments. The installation of the premium overhead cranes was a prerequisite for subsequent equipment setup. Their delivery time directly determined the start dates for all following phases. A single day’s delay would push back the entire project timeline by a day. After evaluating the supplier landscape and the project schedule, the client entrusted us with the full responsibility of ensuring the deadline was met. The sole criterion for the project’s success was whether we could complete the production and shipment of the four cranes during the Spring Festival holiday.
To address the three challenges mentioned above, our response strategy adheres to a core principle: all actions are centered on ensuring no production stoppages, no material shortages, and no delivery delays:

The delivery deadline was incredibly tight this time. There simply wasn’t enough time to spray the company logo on the equipment before it left the factory. Instead of hiding the issue, we were upfront with the client and proposed applying the logo once the facility construction was fully complete. This approach ensured the installation schedule remained on track without compromising the final product’s integrity. The client was understanding and agreed that the plan made sense: get the equipment up and running first, and handle the cosmetic finishing touches once the entire plant was finished. That’s the nature of overseas projects. Candid communication when facing problems is far more important than trying to bluff your way through.
Looking back, that minor hiccup with the logo actually served as a signal. For those few days, no one was concerned with superficial appearances; every ounce of energy was poured into getting the equipment ready on time. The electrical workshop, warehousing, assembly, and quality control teams were all perfectly synchronized. Management streamlined processes and reporting, focusing on a single objective: producing the four cranes. There was no bickering and no waiting around for instructions; everyone knew that the clock was ticking for the four workshops in Kazakhstan.
Completing the factory inspection marked only the halfway point of the project; the remaining half involved cross-border transportation. During the Spring Festival, four 10-ton premium overhead cranes were transported from the manufacturing base in Henan to the client’s factory in Kazakhstan. The route began in Henan, crossed the border at Khorgos (Xinjiang) into Kazakhstan, and covered a total road transport distance of over 4,000 kilometers.
The DAFANGCRANE logistics team secured available transport capacity bound for Central Asia prior to the Spring Festival holiday, immediately upon order confirmation. Packing plans were organized to correspond with the client’s workshop designations: the main steel structure, electrical control cabinets, cabling, and accessories for each crane were consolidated into a single, complete transport unit. Upon arrival, each shipment corresponded to a specific workshop, eliminating the need for the client to perform secondary sorting or redistribution between workshops.
To withstand Kazakhstan’s cold winter climate, all packaging met rigorous cold, and moisture-proofing standards. Documentation required for customs clearance, including certificates of origin, commodity inspection reports, and packing lists, was prepared and verified before the equipment left the factory, ensuring no delays at the border due to paperwork issues.

The results did not disappoint. Four 10-ton premium overhead cranes were completed and shipped to Kazakhstan on schedule. Upon the equipment’s arrival at the site, our technical support team provided remote assistance to the client’s installation team, guiding them through positioning, lifting, and commissioning.
Installation work proceeded simultaneously across four workshop bays. The time elapsed from the initial unloading of equipment to the completion of all commissioning tests was shorter than the client’s original estimate. The electrical system wiring passed inspection on the first attempt, the crane and trolley ran smoothly along their tracks, and all braking test data for the hoisting mechanisms met design standards.
During the acceptance phase, the client’s project manager, Nursultan, commented: “Our biggest concern was that the cranes might become a bottleneck for the entire installation schedule. However, not only did you deliver on time, but the post-delivery commissioning also progressed faster than we anticipated. You were a huge help in ensuring this production line could proceed on schedule.”
The overall construction progress of the factory suffered no delays due to the crane delivery. This is a compelling outcome for an urgent order completed amidst three compounding challenges: the Spring Festival holiday, supply chain constraints, and a sharp rise in copper prices.
If you have a factory construction project underway:
Whether you are operating in Central Asia, Southeast Asia, Africa, or elsewhere, feel free to reach out. We don’t make empty promises or hype things up. We only take on projects we can deliver, and once we commit, we guarantee on-time delivery.
উইচ্যাট