Table of Contents
Single girder overhead crane installation may seem simple — after the main girder, end carriages, electric hoist, and other major components are assembled, the crane is lifted onto the runway rails.
However, we have seen many cases of “installed, but not installed correctly”: the crane running off track and causing rail biting, the hoist swinging from side to side during operation, or bearings making abnormal noises after less than three months of operation. After inspection, the problems are almost never caused by the components themselves. The issues usually come from those installation details that were considered “good enough.”
Therefore, this article does not teach you how to install the crane step by step. Instead, it focuses on the key technical requirements and important inspection points during the single girder overhead crane installation process, such as rail installation, bridge assembly, and electric hoist installation. For example, the height difference at rail joints should be ≤1 mm, and the clearance between the hoist wheel flange and the I-beam should be 3–5 mm.

The first thing the installation team should do after arriving at the site is not to move tools, but to unpack and inspect the equipment.
According to the packing list, check each item one by one: whether the quantity of components is correct, whether there is any damage caused during transportation, and whether all documents (such as certificates of conformity, electrical diagrams, and drawings) are complete.
After checking the delivered components, there is another step that is even more important — inspecting the appearance of the metal structural parts.
Check whether the main girder has been twisted, bent, or impacted during transportation. If these defects are not discovered and corrected on the ground before installation on the runway rails, the cost of handling them after lifting will increase significantly.
During single girder overhead crane unloading and handling, the main concerns are twisting, bending, and impact damage. The correct methods are:

The runway rail is the “road” of the crane. If the road is uneven, even a good vehicle will run poorly.
For single girder overhead cranes, the tolerance control of runway rail installation directly affects the service life of the travel mechanism. Problems such as wheel flange biting, motor overload, and abnormal running noise are mostly caused by rail installation issues.
According to the current standard GB/T 10183.1-2018, the allowable deviation of crane runway span is as follows:
| Span S | Allowable deviation ΔS |
|---|---|
| S ≤ 10 m | ±3 mm |
| S > 10 m | ±[3 + 0.25 × (S − 10)] mm, maximum not exceeding ±15 mm |
For example: For a single girder overhead crane with a span of 20 m, the allowable runway span deviation is:±[3 + 0.25 × (20−10)] = ±5.5 mm. This value is not large, but it must be controlled within the allowable range. Once the deviation exceeds the limit, the friction between the wheel flange and the rail side will increase significantly.
There are two methods for rail joints: straight joints and 45° inclined joints. Inclined joints allow the wheels to pass through the joint more smoothly.
The three key values at the rail joint are:
If any of these three values exceeds the limit, the wheel will “jump” when passing through the joint.
For a fully loaded 10-ton crane passing through this joint hundreds of times every day, the accumulated impact force will cause increasing damage to the wheel bearings.
In addition to joints and span accuracy, several other indicators that are often overlooked are equally important:
The easiest point to overlook is that: The rail ends must be equipped with end stops by welding, and the end stops must make even contact with the crane buffers.
The main girder and end carriages are connected using detachable bolted connections. Although they are separated during transportation from the factory, the installation process at the site requires assembling the complete bridge frame before lifting, rather than assembling individual parts at height.

According to the drawing, place the main girder on two parallel support frames at the same horizontal level. The support frames should be positioned under the stiffening plates at the variable-section areas on both ends of the main girder, and the level should be adjusted properly.

After positioning, the three key steps are:
After tightening is completed, the bridge frame diagonal deviation is one of our mandatory inspection items. If the diagonals of the bridge frame are not equal, the crane will inevitably run off track after being installed on the rails. Measured from the reference points for wheel installation: |E1-E2| ≤ 5 mm

After the single girder overhead crane main girder is lifted to an appropriate height, install the electric hoist directly onto the I-beam rail.

The clearance between the inner side of the hoist wheel flange and the lower flange of the I-beam rail should be 3–5 mm.
Although this value seems small, it directly affects:
The installation of electrical equipment and wiring shall be carried out according to the supplied electrical schematic diagram, wiring diagram, and general electrical equipment drawing. Before installation, the electrical equipment and components shall be inspected:
Before installing the electrical control cabinet, the electrical components and wiring inside the cabinet shall be carefully inspected. The components shall not be damaged, especially the arc extinguishing covers and auxiliary contacts of contactors. The oil stains on the contact surfaces of the contact armature (anti-rust oil is applied before delivery) shall be cleaned.
The inclination of the cabinet surface shall not exceed 5° to ensure the normal operation of the components on the panel.
The following points should be noted during drag cable installation:


After the electrical components have been set according to the requirements, the electrical circuits shall be inspected and adjusted.
First, conduct a complete inspection of the circuit connection points. Confirm that the wiring is correct and tighten all terminal bolts, then switch on the main power supply of the crane.
When checking the operating sequence of the components in the electrical control cabinet, the main circuit breaker should be disconnected. Turn on the control circuit switch, operate the controller handle step by step, and observe whether the operating sequence of each contactor and relay, as well as all electrical interlocks, comply with the requirements of the electrical schematic diagram. If not, identify the cause and make adjustments.
Check and adjust the setting values of all time relays to ensure they meet the values specified in the factory technical documents.
Manually operate each mechanism limit switch and all safety switches, and check whether they operate flexibly. Confirm that when the protected mechanism reaches its limit position, the power supply can be cut off to provide protection. If any fault is found, identify the cause and eliminate it.
Adjustment of motor rotation direction: Close all switches and operate the controller to jog each mechanism motor separately (energize briefly and then immediately cut off the power). Check whether the motor rotation direction is consistent with the operating direction of the controller; whether the two separately driven motors run in the same direction; and whether the rotation direction matches the direction protected by the limit switches. If not, interchange any two phases of the motor stator wiring to make the rotation direction meet the requirements.
After the electrical circuits have been fully inspected, adjusted, and confirmed to be correct, close all circuit breakers to connect the main circuits and control circuits of all mechanisms to the power supply.
First, start each mechanism individually under no-load conditions for trial operation and observe whether each mechanism operates normally. Load operation is only allowed after the no-load operation has been confirmed to be normal. During load operation, the load must be gradually increased until reaching the full load. Direct full-load operation is not allowed. For detailed load testing procedures, please refer to “EOT Crane Load Testing: A Step-by-Step Guide”.
After the trial operation is completed and everything operates normally, the electrical equipment of the crane can be put into normal use.
DAFANG CRANE provides comprehensive single girder overhead crane installation services, including on-site installation guidance by experienced engineers, technical support, equipment commissioning, and trial operation. These services help customers complete crane installation safely and efficiently, ensuring stable and reliable crane performance after operation.
Whether you need our engineers to provide on-site installation services or require remote technical support, we can provide flexible and professional solutions according to your project requirements, helping ensure smooth equipment commissioning and operation.
WeChat